Refinery P&ID Updates

Making PSM Pay

As part of an extensive project to provide record P&ID drawings for Sinclair Corporation’s Rawlings Wyoming Refinery, REDD performed site walks, engineering reviews, and upgraded drawings to “smart” P&ID’s.

Over the life of the project we logged over 115,000 man-hours with no lost time or recordable incidents. We also logged over 160,000 miles without a vehicle accident.

Piping and Instrumentation Diagram (P&ID) Updates

Sinclair Wyoming Refining Company (SWRC) needed to update their Piping & Instrumentation Diagrams (P&IDs) as part of their PSM program and to meet insurance guidelines. As part of the updating process they decided that they wanted to upgrade to “Smart P&IDs”.

SWRC originally hired REDD to perform the field reviews and drafting, but due to demands on their internal technical team they expanded REDD’s scope to also include initial review of process and controls.

After receiving over 1500 updated drawings SWRC has, more efficiently and confidently, been able to facilitate Process Hazard Analyses, resolve core issues in incident investigations, make process improvements and allow for new uses of the drawings including as the base data in the maintenance and operations management software Maximo.

With the benefits realized, SWRC expects to save more in increased efficiency with new “smart P&ID’s” than spent developing them proving once again that PSM Pays.

Additional Resources

Images

full size

CLOSE
full size

CLOSE
full size

CLOSE
full size

CLOSE
full size

CLOSE
full size

CLOSE

Key Personnel

Matthew Hickenlooper

Matthew Hickenlooper

Project Manager

Saul Garcia

Saul Garcia

Senior Designer